Systra UAE
12 - 18 Feb 2026
Week 12 – Crane Capacity for Final Lift
Estimated Time: 6–7 min | PDH/CPD: 1.0 hr | Difficulty: Advanced
Background: The Sombrio bridge is a two-span composite steel plate girder bridge (40 m + 82 m) launched across a deep ravine in Port Renfrew, BC. Four plate girders were incrementally launched without a temporary pier or launch nose, using precast deck panels as tail counterweight, thickened pier-segment bottom flanges, and crane-assisted final lift. (Parameters simplified for conceptual learning. Allow +25% for cross-frames, connection & splice plates. Girders launched without formwork; ignore wind.)
Engineer's Mind: With ~1.0 m tip deflection (Quiz 11), crane lifts tip at 81 m position and holds while girders are pushed final 1 m to 82 m span. System becomes two-span continuous beam: 40 m (launch abutment to pier) + 82 m (pier to crane at far abutment). Using simple tributary method, crane supports approximately half the far span. Calculate end reaction to determine required crane capacity. Simplified rating: (Load × Radius) / 2.5.
Question: Estimate required crane size for final lift where the system transforms to two-span continuous beam: 40 m (launch abutment to pier) + 82 m (pier to far abutment with crane support). Use simple tributary method to determine girder tip load: crane supports half of 82 m span. Given:
Calculation:
Using simple tributary method, crane supports half of 82 m span (~41 m tributary length) = 119 tonnes, plus 5 tonnes for rigging (hook block, slings, spreader bars) = 124 tonnes total. At 6 m radius, simplified formula (Load × Radius / 2.5) requires ~298 tonne-meter capacity. Selection: 300-tonne class provides the required capacity. Crane maintains constant support while the girders are incrementally pushed forward 1 m. The crane sets the girders down onto the permanent bearings. Calculate the actual crane load needed to lift the tip using detailed analysis. Include the extra upward deflection required to position the girder tip above the bearings.