Westmar Advisors Inc.
18 - 24 Dec 2025
Week 6 – Additional Steel Tonnage
Estimated Time: 4–5 min | PDH/CPD: 0.5 hr | Difficulty: Intermediate
Background: The Sombrio bridge is a two-span composite steel plate girder bridge (40 m + 82 m) launched across a deep ravine in Port Renfrew, BC. Four plate girders were incrementally launched without a temporary pier or launch nose, using precast deck panels as tail counterweight, thickened pier-segment bottom flanges, and crane-assisted final lift. (Parameters simplified for conceptual learning. Allow +25% for cross-frames, connection & splice plates. Girders launched without formwork; ignore wind.)
Engineer's Mind: Quiz 5 determined bottom flange must increase from 65 mm to 76 mm for 81 m cantilever capacity. Quantify material impact for steel erector: estimate additional tonnage for procurement, fabrication planning, and cost. Add 20% contingency for conceptual-phase uncertainties (pier segment length, welding details, material wastage).
Question: Calculate total additional steel required (tonnes) for all four girders to strengthen pier segment by increasing bottom-flange thickness from 65 mm to 76 mm. Pier segment is 30 m long per girder. Include 20% contingency. Given:
Calculation:
The 20% contingency accounts for the design risk due to the conceptual nature of calculations. This modest addition (<1% of total bridge steel) could eliminate expensive temporary launching equipment. Critically, added steel provides permanent structural value, unlike throw-away launch nose.