Understanding Pile Group Behavior
Estimated Time: 2-3 min quiz | PDH/CPD: 0.5 hr (incl. review & study) | Difficulty: Intermediate
Question: What’s the primary reason engineers use a pile cap for a group of piles under a bridge pier in saturated clay?
Explanation: A pile cap connects multiple piles into a cohesive unit, distributing the pier’s load evenly among them to prevent differential settlement in saturated clay, where soil strength can vary. It enhances “group efficiency” (how piles share forces per codes like AASHTO) and manages moments from eccentric loads—not reducing pile count (A), which design dictates, nor boosting friction (C), which comes from pile-soil contact. Installation (D) isn’t simpler; it’s an added step.