Temporary Works Responsibility
Estimated Time: 2–3 min | Difficulty: Intermediate
Question
In Design-Bid-Build contracts, temporary works design responsibility lies with:
Explanation:
Temporary works are generally the contractor’s responsibility unless specified otherwise in contract documents.