Wind During Construction
Estimated Time: 2–3 min | Difficulty: Intermediate

Question
Why are wind loads often critical during construction?

  1. Composite action increases stiffness
  2. Dead load is eliminated
  3. Bearings are flexible
  4. Partial stages lack full lateral restraint
Explanation

Explanation:
Temporary stages lack full bracing and composite stiffness, increasing wind sensitivity.