Procurement Risk Allocation
Estimated Time: 2–3 min | Difficulty: Intermediate
Question
In which delivery model does the owner retain primary responsibility for design interpretation?
Explanation:
Under Design-Bid-Build, the owner provides the completed design and retains design liability. In Design-Build, design responsibility shifts to the contractor-led team.